Access to Grid Main Reason for Stall in EU Renewable Deployment

POWER

Access to the power grid is the main reason for the bottleneck of renewable deployment, with rising grid connection queues leading to serious delays in the expansion of wind, European wind lobby group Wind Europe said.

  • Over 500GW of potential wind energy in France, Germany, Italy, Spain, Poland, Romania, Ireland, Croatia, and the UK await grid connection assessments, with Italy and the UK each having over 100GW of pending projects (see chart).
  • The primary reasons are grid saturation and inefficient planning, while national grid expansion targets are typically not aligned with 2030 targets, according to the association.
  • To “unclog” the grid access, grid permitting authorities need to move away from “first come, first served and treat everybody equally”. And system integration would also be good to prioritise.
  • The EU wants to increase its wind energy capacity from 220GW today to 425GW by 2030 and 1.3TW by 2050.

To read the full story

Close

Why MNI

MNI is the leading provider

of intelligence and analysis on the Global Fixed Income, Foreign Exchange and Energy markets. We use an innovative combination of real-time analysis, deep fundamental research and journalism to provide unique and actionable insights for traders and investors. Our "All signal, no noise" approach drives an intelligence service that is succinct and timely, which is highly regarded by our time constrained client base.

Our Head Office is in London with offices in Chicago, Washington and Beijing, as well as an on the ground presence in other major financial centres across the world.