Further Delay to Altamira FLNG but Set for First Full Cargo in June

LNG

The Altamira FLNG facility faces a further start up delay due to a pipe fracture incident according to New Fortress Energy with output expected later in May.

  • The company is however still in the final stages of commissioning, with the first full cargo anticipated in June.
  • The fractured pipe inside the cold box on April 26 has been contained, and repairs are expected to be completed by next weekend, said CEO Chris Guinta.
  • The 1.4mtpa project has faced multiple delays since its initial target of September 2023.
  • First gas was introduced to the plant in December, and the team is working diligently to bring the project online soon.
  • The Altamira project will use US feedgas exported via the Sur de Texas-Tuxpan pipeline through Mexico.

To read the full story

Close

Why MNI

MNI is the leading provider

of intelligence and analysis on the Global Fixed Income, Foreign Exchange and Energy markets. We use an innovative combination of real-time analysis, deep fundamental research and journalism to provide unique and actionable insights for traders and investors. Our "All signal, no noise" approach drives an intelligence service that is succinct and timely, which is highly regarded by our time constrained client base.

Our Head Office is in London with offices in Chicago, Washington and Beijing, as well as an on the ground presence in other major financial centres across the world.