September 04, 2024 15:29 GMT
POWER: PIOSSASCO-GRANDE-ILE 2 Outage Extended Until 27 September
POWER
The unplanned outage at the PIOSSASCO-GRANDE-ILE 2 interconnector has been extended to 27 September, from 6 September previously scheduled, remit data showed.
- Transmission capacity has been reduced to zero in both directions.
- The interconnector first shut down 12:46 CET on 2 September.
41 words