September 25, 2024 15:09 GMT
POWER: Vattenfall, BASF Advance 1.61GW German Offshore Wind Cluster
POWER
Vattenfall, BASF have inched closer to commissioning its 980MW Nordlicht I and 630MW Nordlicht II German offshore wind farms for 2027-28, entering a transport and installation agreement with Havfram, Havfram said today.
- Turbine transport and installation for the Nordlicht 1 will begin in the summer of 2027, with the Nordlicht II beginning in summer 2028.
- Once fully operational, the Nordlicht I and II projects’ combined production is expected to be around 6 TWh/yr.
73 words