September 12, 2024 08:51 GMT
REFINING: Eneos Refinery Updates, Japan:
REFINING
The Eneos Negishi refinery near Tokyo, Japan, shut its 153,000 bpd CDU on September 9 for planned maintenance according to the company.
- The maintenance is planned until mid to late November.
- Eneos has restarted the 136,000 bpd CDU at its Oita refinery on September 1.
- At its Kawasaki refinery near Tokyo, the 172,100-bpd No.2 CDU was brought back online on August 9, while the 77,000-bpd No.3 CDU was restarted on August 29.
- Eneos restarted the 145,000-bpd No.1 CDU at its Sendai refinery in northern Japan on August 15 after suspending it on August 1 due to system issues.
- Eneos conducted an unplanned shutdown of the 175,000-bpd CDU at its Kashima refinery near Tokyo due to a system glitch. No restart date yet scheduled.