Supply Pressure from Norwegian Natural Gas Maintenances Eases

NATURAL GAS

Natural gas supply pressures amid annual maintenance in Norway is starting to ease with the return of the Kollsnes processing plant earlier this week, Gassco remit data showed.

  • The start up of the Oseberg field has been brought forward by one day to 9 July. The field has been partly offline since 29 June with an unavailability of 9.5mcm/d.
  • The maintenance at the Troll field has been extended by four days until 10 July with 21.5mcm/d of unavailable capacity.
  • The 79.8mcm/d Nyhamna processing plant is scheduled to return on 15 July, after an unplanned outage delayed its return from annual maintenance.
  • Pipeline imports from Norway have recovered from lows of below 220mcm/d in June back to 252.2mcm/d today.

To read the full story

Close

Why MNI

MNI is the leading provider

of intelligence and analysis on the Global Fixed Income, Foreign Exchange and Energy markets. We use an innovative combination of real-time analysis, deep fundamental research and journalism to provide unique and actionable insights for traders and investors. Our "All signal, no noise" approach drives an intelligence service that is succinct and timely, which is highly regarded by our time constrained client base.

Our Head Office is in London with offices in Chicago, Washington and Beijing, as well as an on the ground presence in other major financial centres across the world.