New Fortress Energy Aims for First Fast LNG Production in July

LNG

New Fortress Energy plans to complete its first Fast LNG unit in May before moving it to offshore Altamira in Mexico in June and producing LNG in July according to a fourth quarter earnings call on Tuesday.

  • The timeline for the first Fast LNG unit has been delayed from March to May.
  • New Fortress is planning five Fast LNG units with two at Altamira, one to the offshore Lakach gas field in Mexico and two to offshore Louisiana. Each unit will be able to produce 1.4mtpa of LNG from 0.18bcfd of natural gas.
  • LNG from Louisiana was originally targeted for Q1 2023 but regulator delays mean the project could be approved in September according to ClearView Energy Partners LLC.

To read the full story

Close

Why MNI

MNI is the leading provider

of intelligence and analysis on the Global Fixed Income, Foreign Exchange and Energy markets. We use an innovative combination of real-time analysis, deep fundamental research and journalism to provide unique and actionable insights for traders and investors. Our "All signal, no noise" approach drives an intelligence service that is succinct and timely, which is highly regarded by our time constrained client base.

Our Head Office is in London with offices in Chicago, Washington and Beijing, as well as an on the ground presence in other major financial centres across the world.