POWER: Belgium Delays 3.5GW Princess Elisabeth Island Project by Three Years
POWER
Belgium’s Elia (ETB) has delayed the 3.5GW Princess Elisabeth Island project by around three years as the signing of high-voltage direct current (HVDC) contracts for the park was postponed due to soaring costs and market volatility, it said.
- Elia was hoping to connect the wind farms to the onshore grid by 2030, with the delay pushing it back to around 2033.
- The deadline to award the contract was set for mid-February 2025 and was imposed by the supplier.
- The move is due to a significant cost increase in HVDC technology due to supply chain challenges and inflation.
- The postponement provides the Belgian government with additional time to assess various options and implement necessary regulatory adjustments, Elia added.
- Meanwhile, alternative designs are being explored, though they come with uncertainties related to policy and regulation.
- However, the construction of Princess Elisabeth Island and the execution of alternating current (AC) contracts are moving forward as scheduled.
- And at the same time, work on two offshore wind farms is progressing, already accounting for 60% of the new Princess Elisabeth wind zone.
- The project will consist of a 700MW wind farm and two 1.4GW wind units.