POWER: Capacity on 350MW Estlink 1 To Be Lowered Over 8-10 Feb Amid Iso Testing

POWER

Capacity on the 350MW Estlink 1 power cable between Finland-Estonian will be reduced to 150MW over 8-10 February due to the Baltic isolation test over the period, latest Remit data show.

  • Capacity on the link will drop to 248MW on 8 February between 00:00-01:00CET before being lowered to 150MW over 01:00CET 8 February and 10 February 00:00CET.
  • The test is done to ensure Baltic frequency stability ahead of synchronisation with the EU grid on 9 February.
  • Capacity is lowered in both directions.
  • The 650MW Estlink 2 is still disconnected until 31 July.
88 words

To read the full story

Close

Why MNI

MNI is the leading provider

of intelligence and analysis on the Global Fixed Income, Foreign Exchange and Energy markets. We use an innovative combination of real-time analysis, deep fundamental research and journalism to provide unique and actionable insights for traders and investors. Our "All signal, no noise" approach drives an intelligence service that is succinct and timely, which is highly regarded by our time constrained client base.

Our Head Office is in London with offices in Chicago, Washington and Beijing, as well as an on the ground presence in other major financial centres across the world.

Capacity on the 350MW Estlink 1 power cable between Finland-Estonian will be reduced to 150MW over 8-10 February due to the Baltic isolation test over the period, latest Remit data show.

  • Capacity on the link will drop to 248MW on 8 February between 00:00-01:00CET before being lowered to 150MW over 01:00CET 8 February and 10 February 00:00CET.
  • The test is done to ensure Baltic frequency stability ahead of synchronisation with the EU grid on 9 February.
  • Capacity is lowered in both directions.
  • The 650MW Estlink 2 is still disconnected until 31 July.