Finland Restarts works at Finnish-Swedish Power Link

POWER

Finnish TSO Fingrid has restarted works on the FI-SE1 interconnector after suspending maintenance on Tuesday due to the unplanned outage at the 1.6GW OL3 nuclear power plant on Monday, the TSO said.

  • The power link is expected to complete works on 23 June.
  • The interconnector has 1.1GW of capacity towards FI-SE1 and 1.5GW in the other direction. Capacity is currently lowered by 0.800-1.3GW.
  • The 1.2GW FI-SE3 interconnector is also undergoing planned works until 14 June - capacity is lowered by 400MW over the period.

To read the full story

Close

Why MNI

MNI is the leading provider

of intelligence and analysis on the Global Fixed Income, Foreign Exchange and Energy markets. We use an innovative combination of real-time analysis, deep fundamental research and journalism to provide unique and actionable insights for traders and investors. Our "All signal, no noise" approach drives an intelligence service that is succinct and timely, which is highly regarded by our time constrained client base.

Our Head Office is in London with offices in Chicago, Washington and Beijing, as well as an on the ground presence in other major financial centres across the world.