Vattenfall’’s 1.17GW Forsmark Block 3 nuclear reactor is now scheduled to resume full output a day later on 5 February amid an unplanned outage, remit data showed.
- The unit was originally scheduled to return with full capacity on 4 February.
- An unplanned outage from 17:000CET on Monday is reducing output by 822MW until 18:00CET. After that, output will be curtailed by 472MW until 10:00CET on 5 February.
- Capacity at the plant had been curtailed due to valve problems.