November 12, 2024 09:12 GMT
LNG: Ichthys LNG Train 1 to Restart in December
LNG
Further info on Ichthys LNG: Inpex will now ramp up Train 1 to full capacity in early December, instead of mid-November as originally planned according to Daisuke Yamada, a senior executive at the company, said on Tuesday.
- The train has been operating at reduced rates since September because of an inspection to see if Train 1 had the same issues that halted Train 2.
- The Ichthys facility is running at around 85% at present.
74 words