AMERICAS OIL: New Fortress Energy to start construction of LNG plant in Mexico

AMERICAS OIL

New Fortress Energy to start construction of US$1bn LNG plant in Mexico: BNamericas

  • US natural gas firm New Fortress Energy will begin onshore construction of its second LNG plant at the Mexican port of Altamira by mid-year.
  • "We currently expect onshore construction to commence this summer and are working closely with CFE on that process and [will] provide additional updates as permits are received," CFO Chris Guinta told a recent Q4 earnings call.
  • “Construction of the modules is now over 50% complete,” Guinta said.
  • NFE began operations at its first plant at Altamira, a floating LNG facility named FLNG1, with capacity to produce 1.4Mt/y in July 2024. There have been 12 cargoes shipped from the plant.
  • For the second plant, FLNG2, NFE is converting an onshore import terminal built by Shell into an LNG export terminal. FLNG2 will have the same capacity as FLNG1.
141 words

To read the full story

Close

Why MNI

MNI is the leading provider

of intelligence and analysis on the Global Fixed Income, Foreign Exchange and Energy markets. We use an innovative combination of real-time analysis, deep fundamental research and journalism to provide unique and actionable insights for traders and investors. Our "All signal, no noise" approach drives an intelligence service that is succinct and timely, which is highly regarded by our time constrained client base.

Our Head Office is in London with offices in Chicago, Washington and Beijing, as well as an on the ground presence in other major financial centres across the world.

New Fortress Energy to start construction of US$1bn LNG plant in Mexico: BNamericas

  • US natural gas firm New Fortress Energy will begin onshore construction of its second LNG plant at the Mexican port of Altamira by mid-year.
  • "We currently expect onshore construction to commence this summer and are working closely with CFE on that process and [will] provide additional updates as permits are received," CFO Chris Guinta told a recent Q4 earnings call.
  • “Construction of the modules is now over 50% complete,” Guinta said.
  • NFE began operations at its first plant at Altamira, a floating LNG facility named FLNG1, with capacity to produce 1.4Mt/y in July 2024. There have been 12 cargoes shipped from the plant.
  • For the second plant, FLNG2, NFE is converting an onshore import terminal built by Shell into an LNG export terminal. FLNG2 will have the same capacity as FLNG1.