Norway to Denmark Gas Delayed - Poland Unaffected

NATURAL GAS

The opening of the Danish terminal Nybro by Varde for Norwegian gas has been delayed by almost two weeks to November 1 according to Energinet.

  • The receiving terminal for gas from the Norwegian gas pipeline Europipe II should have gone into operation on Thursday 20 October 2022.
  • Energinet announced to the gas market that commissioning of Nybro will take place in two stages: commissioning is expected on 1 November 2022 with half of the total capacity (6,700 MWh/h). Full commissioning will take place later in 2022. A date is yet to be confirmed for full commissioning.
  • The delay in Nybro will not affect the gas volume to Poland. As planned, the Baltic Pipe was put into operation at partial capacity on Saturday 1 October.
  • The recently opened Baltic Pipe has allowed Poland to transition away from Russian gas which was cut off earlier this year.

To read the full story

Close

Why MNI

MNI is the leading provider

of intelligence and analysis on the Global Fixed Income, Foreign Exchange and Energy markets. We use an innovative combination of real-time analysis, deep fundamental research and journalism to provide unique and actionable insights for traders and investors. Our "All signal, no noise" approach drives an intelligence service that is succinct and timely, which is highly regarded by our time constrained client base.

Our Head Office is in London with offices in Chicago, Washington and Beijing, as well as an on the ground presence in other major financial centres across the world.