REFINING: PBF Martinez Refinery Damage Assessment May Take Weeks

REFINING

The PBF Energy 156k b/d Martinez refinery near San Francisco may need 45 days or more to assess the damage from a fire on Feb. 1, according to Bloomberg sources.

  • The refinery was shut after a fire in the Light Oil Processing section area where gasoline is made after a leak of hydrocarbons, the sources said.
  • Initial assessment shows extensive damage to the cat feed hydrotreater, where the fire originated, that may not be repairable.
  • Other units, including the alkylation unit, hydrogen units and sulfur recovery units appear to also have suffered damage.
  • Repairing the fire-damaged area delayed beginning a 55-65 day multi-unit turnaround that was scheduled to start Feb. 3
107 words

To read the full story

Close

Why MNI

MNI is the leading provider

of intelligence and analysis on the Global Fixed Income, Foreign Exchange and Energy markets. We use an innovative combination of real-time analysis, deep fundamental research and journalism to provide unique and actionable insights for traders and investors. Our "All signal, no noise" approach drives an intelligence service that is succinct and timely, which is highly regarded by our time constrained client base.

Our Head Office is in London with offices in Chicago, Washington and Beijing, as well as an on the ground presence in other major financial centres across the world.

The PBF Energy 156k b/d Martinez refinery near San Francisco may need 45 days or more to assess the damage from a fire on Feb. 1, according to Bloomberg sources.

  • The refinery was shut after a fire in the Light Oil Processing section area where gasoline is made after a leak of hydrocarbons, the sources said.
  • Initial assessment shows extensive damage to the cat feed hydrotreater, where the fire originated, that may not be repairable.
  • Other units, including the alkylation unit, hydrogen units and sulfur recovery units appear to also have suffered damage.
  • Repairing the fire-damaged area delayed beginning a 55-65 day multi-unit turnaround that was scheduled to start Feb. 3