January 20, 2025 10:50 GMT
POWER: Polish 534MW Coal Unit Suffers Unplanned Outage
POWER
Poland’s 534MW unit 10 at its 2.2GW Kozienice 2 coal plant has had an unplanned outage today, with the unit disconnected until 23 January, latest Remit data show.
- The unit was disconnected due to “emergence repairs,” according to Remit remarks.
- Additionally, unplanned works at the 210MW unit 2 of the 1.8GW Kozienice 1 coal plant is due to end on 22 January,