November 08, 2024 08:12 GMT
POWER: Forsmark 3 Extends Works to Jan 25, Forsmark 1 has Unplanned Curtailment
POWER
The 1.17GW Forsmark 3 has extended its outage by just over one month to 27 January 2025 as further work is needed, while the 1.1GW Forsmark unit 1 has had an unplanned 160MW curtailment, with the duration unknown, latest Remit data show.
- Forsmark unit 3 was meant to return to the grid on 16 December 2024.
- The curtailment at the Forsmark unit 1 is due to “failure on turbine.”
67 words