POWER: UPDATE- OL3 Return Pushed Back Until 4 October
POWER
The planned return of the 1.6GW Ol3 nuclear power plant is now anticipated on 4 October 15:00 BST, from 3 October 23:00 BST previously scheduled, remit data showed.
- The reactor will have 380MW of capacity unavailable until 18:00 BST, 310MW unavailable until 3 October 30:00 BST, 200MW unavailable until 08:00 BST on 4 October and 105MW unavailable until 4 October 15:00 BST.