September 20, 2024 07:02 GMT
POWER: Vattenfall Extends Works at 1.1GW Nuke
POWER
Vattenfall has extended works at its 1.17GW Forsmark nuclear unit 3 to 28 October from 18 October due to “additional work,” latest Remit data show.
- The unit has been offline since the 1 Sept and is located in the SE3 bidding zone.
41 words