RENEWABLES: SSE Delays 1.2GW Dogger Bank A Completion to 2H25

RENEWABLES

SSE has delayed the completion of the 1.2GW Dogger Bank A offshore wind project to 2H 2025, from 1H 2025 previously scheduled, the firm said, cited by Reuters. 

  • The firm said earlier this year that challenging weather conditions had impacted turbine installations, while vessel availability and supply chain delays also impacted the construction process. 
54 words

To read the full story

Close

Why MNI

MNI is the leading provider

of intelligence and analysis on the Global Fixed Income, Foreign Exchange and Energy markets. We use an innovative combination of real-time analysis, deep fundamental research and journalism to provide unique and actionable insights for traders and investors. Our "All signal, no noise" approach drives an intelligence service that is succinct and timely, which is highly regarded by our time constrained client base.

Our Head Office is in London with offices in Chicago, Washington and Beijing, as well as an on the ground presence in other major financial centres across the world.

SSE has delayed the completion of the 1.2GW Dogger Bank A offshore wind project to 2H 2025, from 1H 2025 previously scheduled, the firm said, cited by Reuters. 

  • The firm said earlier this year that challenging weather conditions had impacted turbine installations, while vessel availability and supply chain delays also impacted the construction process.