Tyra Peak Production Delayed to Q4 Amid Technical issues

NATGAS

Denmark's Tyra natural gas field requires repairs to a power transformer delivering power to the intermediate pressure gas compressor, according to operator TotalEnergies.

  • The field will only reach peak production in Q4 instead of mid-year due to the technical issues. In March, the company expected the field to reach the technical capacity of 8.1mcm/d in four months.
  • The commissioning of the facilities and gas exports from Tyra continue at present levels while the repair work is ongoing.
  • Gas volumes may be redirected to Den Helder, the Netherlands, during remediation while different options to deliver additional gas volumes to Denmark are being explored.
  • BlueNord, a partner in the development, expects the restart of gas export from Tyra II in July and for an increase through Q3.
  • The Tyra field restart would make Denmark self-sufficient and a net exporter of natural gas.

To read the full story

Close

Why MNI

MNI is the leading provider

of intelligence and analysis on the Global Fixed Income, Foreign Exchange and Energy markets. We use an innovative combination of real-time analysis, deep fundamental research and journalism to provide unique and actionable insights for traders and investors. Our "All signal, no noise" approach drives an intelligence service that is succinct and timely, which is highly regarded by our time constrained client base.

Our Head Office is in London with offices in Chicago, Washington and Beijing, as well as an on the ground presence in other major financial centres across the world.