POWER: Unplanned Outage at Poland’s 910MW Jaworzno 2 Extended to 13 Feb
POWER
OUTAGE UPDATE- The unplanned outage at Poland’s 910MW Jaworzno 2 coal plant has been extended to 13 February from 12 February, however, the unit will is still curtailed by 454MW, latest Remit data show.
- The unit was fully disconnected on 29 January due to “emergency repairs,” and was meant to fully return to the grid on 3 February.