Norway Gas Maintenance: Norway Gas Outages to Ease During this Week

NATGAS

Norwegian pipeline supplies to Europe are today nominated at 269.1mcm/d with field and processing plant capacity outages totalling 101.7mcm/d today according to Gassco data. Outages due to planned maintenance are expected to ease slightly in the coming days.

  • Dvalin will have 9mcm/d of unavailable capacity from 23 April until 1 May and 5-8 May. Additional works are scheduled to take place in the first half of May.
  • The Nyhamna processing facility will have a reduced capacity of 35.8mcm/d from 24 April until April 30.
  • Aasta Hansteen field will have a reduced capacity of 25.5mcm/d for works on 26 April until 1 May and 12.0mcm/d from 1 May to 2 May.
  • The Karsto processing facility will reduce capacity by 12.1mcm on 27-30 April and on 4-6 May.
  • The Kollsnes processing facility will reduce capacity by 42mcm/d from 27 April until 10 May.
  • Troll will have a reduced capacity of 43mcm/d for works on 27 April until 2 May and 39.0mcm/d from 2 May to 10 May.
  • Gulfaks will have 6.4mcm/d of unavailable capacity from 2-6 May.

Keep reading...Show less
176 words

To read the full story

Close

Why MNI

MNI is the leading provider

of intelligence and analysis on the Global Fixed Income, Foreign Exchange and Energy markets. We use an innovative combination of real-time analysis, deep fundamental research and journalism to provide unique and actionable insights for traders and investors. Our "All signal, no noise" approach drives an intelligence service that is succinct and timely, which is highly regarded by our time constrained client base.

Our Head Office is in London with offices in Chicago, Washington and Beijing, as well as an on the ground presence in other major financial centres across the world.

Norwegian pipeline supplies to Europe are today nominated at 269.1mcm/d with field and processing plant capacity outages totalling 101.7mcm/d today according to Gassco data. Outages due to planned maintenance are expected to ease slightly in the coming days.

  • Dvalin will have 9mcm/d of unavailable capacity from 23 April until 1 May and 5-8 May. Additional works are scheduled to take place in the first half of May.
  • The Nyhamna processing facility will have a reduced capacity of 35.8mcm/d from 24 April until April 30.
  • Aasta Hansteen field will have a reduced capacity of 25.5mcm/d for works on 26 April until 1 May and 12.0mcm/d from 1 May to 2 May.
  • The Karsto processing facility will reduce capacity by 12.1mcm on 27-30 April and on 4-6 May.
  • The Kollsnes processing facility will reduce capacity by 42mcm/d from 27 April until 10 May.
  • Troll will have a reduced capacity of 43mcm/d for works on 27 April until 2 May and 39.0mcm/d from 2 May to 10 May.
  • Gulfaks will have 6.4mcm/d of unavailable capacity from 2-6 May.