PGE to Commission PGE Gryfino 2050 CCGT Plants in Aug, Sept

POWER

Poland’s PGE is scheduled to commission its two CCGT units at the PGE Gryfino 2050 power plant in August and September, it said in a filing.

  • The 683MW Unit 9 is scheduled to commissioned on 15 August and Unit 10 will be commissioned on 30 September – both with a 35-day joint grace period.
  • The firm added that operational milestone requirements for the units have been met, which enabled the firm to receive revenues from the capacity market.

To read the full story

Close

Why MNI

MNI is the leading provider

of intelligence and analysis on the Global Fixed Income, Foreign Exchange and Energy markets. We use an innovative combination of real-time analysis, deep fundamental research and journalism to provide unique and actionable insights for traders and investors. Our "All signal, no noise" approach drives an intelligence service that is succinct and timely, which is highly regarded by our time constrained client base.

Our Head Office is in London with offices in Chicago, Washington and Beijing, as well as an on the ground presence in other major financial centres across the world.