Free Trial

POWER: Poland 58% Ready for 3.75GW Nuclear Plant But Challenges Persists

POWER

 Poland is 58% ready to begin construction on its first large-scale nuclear power plant, which will have a total capacity of 3.75GW, according to a new report by Baker McKenzie and Polityka Insight, cited by ISB News.

  • However, while the country has made significant progress in regulatory, political, and social readiness, challenges remain in technology, investment, and workforce development, which could delay the project’s timeline, the report added.
  • Additionally, further legislative refinements are needed, including insurance pools and local content rules.
  • And licensing process for the selected reactor is still pending, delaying component procurement.
  • Contract signing for reactor construction is expected by 2028-2029, three years later than planned, the report said.
  • Furthermore, the European Commission’s state aid approval process could take longer than the formal 18-month timeline, the authors highlighted.
  • Poland is eyeing a total nuclear capacity of around 6-9GW in the upcoming decades, with the first unit expected to be operational in the mid-2030s.
149 words

To read the full story

Close

Why MNI

MNI is the leading provider

of intelligence and analysis on the Global Fixed Income, Foreign Exchange and Energy markets. We use an innovative combination of real-time analysis, deep fundamental research and journalism to provide unique and actionable insights for traders and investors. Our "All signal, no noise" approach drives an intelligence service that is succinct and timely, which is highly regarded by our time constrained client base.

Our Head Office is in London with offices in Chicago, Washington and Beijing, as well as an on the ground presence in other major financial centres across the world.

 Poland is 58% ready to begin construction on its first large-scale nuclear power plant, which will have a total capacity of 3.75GW, according to a new report by Baker McKenzie and Polityka Insight, cited by ISB News.

  • However, while the country has made significant progress in regulatory, political, and social readiness, challenges remain in technology, investment, and workforce development, which could delay the project’s timeline, the report added.
  • Additionally, further legislative refinements are needed, including insurance pools and local content rules.
  • And licensing process for the selected reactor is still pending, delaying component procurement.
  • Contract signing for reactor construction is expected by 2028-2029, three years later than planned, the report said.
  • Furthermore, the European Commission’s state aid approval process could take longer than the formal 18-month timeline, the authors highlighted.
  • Poland is eyeing a total nuclear capacity of around 6-9GW in the upcoming decades, with the first unit expected to be operational in the mid-2030s.