European Gas Maintenance Update

NATURAL GAS

Maintenance at Norway’s Troll field next will be smaller than initially planned, after an ongoing series of works will end two days earlier than expected. Capacity reductions will significantly deepen from 26 August, Gassco remit data showed.

  • The Troll field will end the current maintenance affecting 17.5mcm/d on Monday. Capacity will be reduced by 5.5mcm/d on 14-19 August before rising to 34.5mcm/d on 19-26 August.
  • Works at the Ormen Lange field have been extended for 19-20 and 20-21 August.
  • The Kollsnes processing plant is scheduled to return on 21 August. Output has been reduced by 10mcm/d.
  • Prior to the changes to the schedule, an RBC note estimated 1.5bcm of production is expected to be offline during August and 2.5bcm in September, with the main bulk of outages starting from 26 August.
  • In the UK, gas works at the St Fergus terminal have been extended until 1 September.
  • The Cygnus field is scheduled to come back two days later than originally planned on 15 August.
  • The Perenco Bacton terminal will end maintenance on 15 August.
  • In Germany, there was no LNG sendout on 10-11 August at the Brunsbuettel LNG terminal.

To read the full story

Close

Why MNI

MNI is the leading provider

of intelligence and analysis on the Global Fixed Income, Foreign Exchange and Energy markets. We use an innovative combination of real-time analysis, deep fundamental research and journalism to provide unique and actionable insights for traders and investors. Our "All signal, no noise" approach drives an intelligence service that is succinct and timely, which is highly regarded by our time constrained client base.

Our Head Office is in London with offices in Chicago, Washington and Beijing, as well as an on the ground presence in other major financial centres across the world.