The outage at the 658MW Estlink 2 between Finland and Estonia on 25 December has been extended until 31 July 2025, according to the latest Remit data.

  • The outage was originally supposed to last until the end of 25 December but was extended to 26 December before being pushed back to 31 December.
  • The outage is due to a cable failure at the subsea connection in the northern Gulf of Finland, not onshore.
  • The outage will not prevent the planned disconnection of the Baltic states from the Russian power network set for early February 2025, TSO Elering said.
95 words

To read the full story

Close

Why MNI

MNI is the leading provider

of intelligence and analysis on the Global Fixed Income, Foreign Exchange and Energy markets. We use an innovative combination of real-time analysis, deep fundamental research and journalism to provide unique and actionable insights for traders and investors. Our "All signal, no noise" approach drives an intelligence service that is succinct and timely, which is highly regarded by our time constrained client base.

Our Head Office is in London with offices in Chicago, Washington and Beijing, as well as an on the ground presence in other major financial centres across the world.

The outage at the 658MW Estlink 2 between Finland and Estonia on 25 December has been extended until 31 July 2025, according to the latest Remit data.

  • The outage was originally supposed to last until the end of 25 December but was extended to 26 December before being pushed back to 31 December.
  • The outage is due to a cable failure at the subsea connection in the northern Gulf of Finland, not onshore.
  • The outage will not prevent the planned disconnection of the Baltic states from the Russian power network set for early February 2025, TSO Elering said.