POWER: Netheland's Extends Outage at 350MW Gas Unit to 3 March
POWER
The Netherlands’ 356MW EEMS 3 gas-fired unit has extended its planned works again to 3 March from 17 February, latest Remit data show.
- The unit was shut off on 8 February at 08:00 CET and will remain offline until 3 March at 00:00 CET.
- Full capacity is now expected to be reached on 3 March at 01:14 CET.