POWER: EnBW’s Grid Stabilization Plant March 4 to Start End September

POWER

EnBW’s 300MW Marbach 4 grid stabilisation gas plant will be handed over to the grid operator on 30 September, after being in a commissioning phase since 17 July, remit data showed. 

  • Previously, the plant was scheduled to be handed over on 16 September. 
  • Germany’s Bnetza decided to have new generation plants built in southern Germany following the phase out of nuclear energy, the increased use of renewable power and the insufficiently quick grid expansion. 
  • The plant was initially scheduled to start commercial operations in October 2022 but global delivery problems, material supply bottlenecks, plant closures and staff shortages have delayed construction works, EnBW said. 

To read the full story

Close

Why MNI

MNI is the leading provider

of intelligence and analysis on the Global Fixed Income, Foreign Exchange and Energy markets. We use an innovative combination of real-time analysis, deep fundamental research and journalism to provide unique and actionable insights for traders and investors. Our "All signal, no noise" approach drives an intelligence service that is succinct and timely, which is highly regarded by our time constrained client base.

Our Head Office is in London with offices in Chicago, Washington and Beijing, as well as an on the ground presence in other major financial centres across the world.