POWER: UK Network Operators Abolish 10GW of “Zombie” Projects

POWER

UK power network operators have cut 10GW of stalled “zombie” energy projects in a bid to increase the connection process, figures from Energy Networks Association show.

  • However, there is still around 252GW of more generation units in the queue than required to meet the UK’s 2050 Net Zero goals, the association added.
  • The Energy Network association is taking steps to curtail these so-called “zombie” projects by:
  • Ensuring all projects in the queue meet their milestones.
  • For delayed projects, network companies discuss reasons and assist in progression.
  • Stalled projects are removed from the queue and contracts are terminated.
92 words

To read the full story

Close

Why MNI

MNI is the leading provider

of intelligence and analysis on the Global Fixed Income, Foreign Exchange and Energy markets. We use an innovative combination of real-time analysis, deep fundamental research and journalism to provide unique and actionable insights for traders and investors. Our "All signal, no noise" approach drives an intelligence service that is succinct and timely, which is highly regarded by our time constrained client base.

Our Head Office is in London with offices in Chicago, Washington and Beijing, as well as an on the ground presence in other major financial centres across the world.

UK power network operators have cut 10GW of stalled “zombie” energy projects in a bid to increase the connection process, figures from Energy Networks Association show.

  • However, there is still around 252GW of more generation units in the queue than required to meet the UK’s 2050 Net Zero goals, the association added.
  • The Energy Network association is taking steps to curtail these so-called “zombie” projects by:
  • Ensuring all projects in the queue meet their milestones.
  • For delayed projects, network companies discuss reasons and assist in progression.
  • Stalled projects are removed from the queue and contracts are terminated.