Corpus Christi LNG Stage 3 is 53% Complete as Production Targeted This Year

LNG

Cheniere’s Corpus Christi LNG stage 3 expansion project in Texas is 52.7% percent complete according to LNG Prime citing the January construction report filed with the US FERC last week.

  • The US LNG facility is targeting the start of production at the first train later this year. LNG deliveries were initially targeted to begin in 2025 with full production in 2027 but CEO Jack Fusco said in August that the expansion project is expected to complete ahead of schedule.
  • Corpus Christi Stage 3 will consist of seven “midscale” trains that will add approximately 10+mtpa of production capacity, bringing CCL’s total nominal capacity to more than 25mtpa.
  • Two more midscale trains 8 & 9 are planned as part of the third expansion phase with FID in 2025, subject to regulatory approvals.

To read the full story

Close

Why MNI

MNI is the leading provider

of intelligence and analysis on the Global Fixed Income, Foreign Exchange and Energy markets. We use an innovative combination of real-time analysis, deep fundamental research and journalism to provide unique and actionable insights for traders and investors. Our "All signal, no noise" approach drives an intelligence service that is succinct and timely, which is highly regarded by our time constrained client base.

Our Head Office is in London with offices in Chicago, Washington and Beijing, as well as an on the ground presence in other major financial centres across the world.