Gimi FLNG Arrives at BP Senegal Project as Scheduled

LNG

The Gimi floating LNG production unit for BP's 2.5mtpa Tortue LNG project off Senegal arrived on schedule today according to ICIS.

  • The vessel will wait by Tenerife as the project is not yet ready to begin.
  • The vessel is due to operate on the Greater Tortue Ahmeyim field for the next 20 years.
  • The project is due to startup later in 2024 after delays, including to pipeline construction, pushed back the operations from a late 2023 start.
  • BP has had to pick a new company to complete laying the offshore pipelines.

To read the full story

Close

Why MNI

MNI is the leading provider

of intelligence and analysis on the Global Fixed Income, Foreign Exchange and Energy markets. We use an innovative combination of real-time analysis, deep fundamental research and journalism to provide unique and actionable insights for traders and investors. Our "All signal, no noise" approach drives an intelligence service that is succinct and timely, which is highly regarded by our time constrained client base.

Our Head Office is in London with offices in Chicago, Washington and Beijing, as well as an on the ground presence in other major financial centres across the world.