POWER: 1GW FR-GB ElecLink Extends Works Further to 2 December

POWER

Planned works at the 1GW Eleclink power cable between France and the UK have been extended to 2 Dec from 22 Nov, latest Remit data show.

  • The power link was originally expected back online on 16 Nov and was then pushed back to 19 Nov and then further delayed to 22 Nov. It was disconnected on 12 Oct.
  • No capacity is available in both directions.
  • However, the IFA2 interconnector between the two countries remains on track to return on 17 November after an unplanned outage.
82 words

To read the full story

Close

Why MNI

MNI is the leading provider

of intelligence and analysis on the Global Fixed Income, Foreign Exchange and Energy markets. We use an innovative combination of real-time analysis, deep fundamental research and journalism to provide unique and actionable insights for traders and investors. Our "All signal, no noise" approach drives an intelligence service that is succinct and timely, which is highly regarded by our time constrained client base.

Our Head Office is in London with offices in Chicago, Washington and Beijing, as well as an on the ground presence in other major financial centres across the world.

Planned works at the 1GW Eleclink power cable between France and the UK have been extended to 2 Dec from 22 Nov, latest Remit data show.

  • The power link was originally expected back online on 16 Nov and was then pushed back to 19 Nov and then further delayed to 22 Nov. It was disconnected on 12 Oct.
  • No capacity is available in both directions.
  • However, the IFA2 interconnector between the two countries remains on track to return on 17 November after an unplanned outage.