POWER: Finland, Sweden Delay Plan to Reduce HVDC Cable Strain via Market Trading

POWER

 Fingrid is postponing the introduction of a new procedure aimed at reducing transmission direction changes in power cables due to additional system development required by Svenska Kraftnat, the TSO said.

  • Frequent changes in transmission direction put stress on HVDC cables, which can shorten their service life, according to Fingrid.
  • Fingrid and Svenska Kraftnat plan to engage in intraday market trading to limit transmission direction changes.
  • Additionally, to prevent additional changes, the TSO will pre-limit cross-border transmission capacity in the intraday market.
  • Fingrid will trade electricity as needed, with any remaining needs met through balancing market adjustments or firm transactions, according to the TSO
  • The changes were meant to be implemented on 18 March 2025 but a new date  will be announced once the necessary updates are completed.
122 words

To read the full story

Close

Why MNI

MNI is the leading provider

of intelligence and analysis on the Global Fixed Income, Foreign Exchange and Energy markets. We use an innovative combination of real-time analysis, deep fundamental research and journalism to provide unique and actionable insights for traders and investors. Our "All signal, no noise" approach drives an intelligence service that is succinct and timely, which is highly regarded by our time constrained client base.

Our Head Office is in London with offices in Chicago, Washington and Beijing, as well as an on the ground presence in other major financial centres across the world.

 Fingrid is postponing the introduction of a new procedure aimed at reducing transmission direction changes in power cables due to additional system development required by Svenska Kraftnat, the TSO said.

  • Frequent changes in transmission direction put stress on HVDC cables, which can shorten their service life, according to Fingrid.
  • Fingrid and Svenska Kraftnat plan to engage in intraday market trading to limit transmission direction changes.
  • Additionally, to prevent additional changes, the TSO will pre-limit cross-border transmission capacity in the intraday market.
  • Fingrid will trade electricity as needed, with any remaining needs met through balancing market adjustments or firm transactions, according to the TSO
  • The changes were meant to be implemented on 18 March 2025 but a new date  will be announced once the necessary updates are completed.