March 05, 2025 10:09 GMT
POWER: Finland, Sweden Delay Plan to Reduce HVDC Cable Strain via Market Trading
POWER
Fingrid is postponing the introduction of a new procedure aimed at reducing transmission direction changes in power cables due to additional system development required by Svenska Kraftnat, the TSO said.
- Frequent changes in transmission direction put stress on HVDC cables, which can shorten their service life, according to Fingrid.
- Fingrid and Svenska Kraftnat plan to engage in intraday market trading to limit transmission direction changes.
- Additionally, to prevent additional changes, the TSO will pre-limit cross-border transmission capacity in the intraday market.
- Fingrid will trade electricity as needed, with any remaining needs met through balancing market adjustments or firm transactions, according to the TSO
- The changes were meant to be implemented on 18 March 2025 but a new date will be announced once the necessary updates are completed.
122 words