Norway Gas: Troll and Kollsnes Works Raise Outages to 177mcm/d

NATGAS

Norwegian pipeline supplies to Europe are nominated down at 178.9mcm/d with works today at Troll and Kollsnes but the facilities are gradually returning during the week. Gassco data shows total outages of 177mcm/d today declining back to around 55mcm/d later this week.

  • Visund field will have a reduced capacity of 16mcm/d from 8 May to 5 June.
  • Gullfaks will have 9.2mcm/d of unavailable capacity from 9 May to 4 June.
  • The Karsto processing facility will reduce capacity by 12.6mcm/d from 19 May to 1 June, 6.6mcm/d from 20-23 My and 17.6mcm/d on 20-23 May and with further outages scheduled in late May.
  • Troll will have a reduced capacity of 133mcm/d from 21-22 May, 46mcm/d on 22-23 May and 24 mcm/d from 23-24 May, and 19 mcm/d from 24-31 May.
  • The Kollsnes processing facility will reduce capacity by 158mcm/d on 21-22 May, 66mcm/d on 22-23 May and 42mcm/d on 23 May to 4 June.
  • Kvitebjørn will have a reduced capacity of 8.5mcm/d on 21-24 May.

Keep reading...Show less
171 words

To read the full story

Close

Why MNI

MNI is the leading provider

of intelligence and analysis on the Global Fixed Income, Foreign Exchange and Energy markets. We use an innovative combination of real-time analysis, deep fundamental research and journalism to provide unique and actionable insights for traders and investors. Our "All signal, no noise" approach drives an intelligence service that is succinct and timely, which is highly regarded by our time constrained client base.

Our Head Office is in London with offices in Chicago, Washington and Beijing, as well as an on the ground presence in other major financial centres across the world.

Norwegian pipeline supplies to Europe are nominated down at 178.9mcm/d with works today at Troll and Kollsnes but the facilities are gradually returning during the week. Gassco data shows total outages of 177mcm/d today declining back to around 55mcm/d later this week.

  • Visund field will have a reduced capacity of 16mcm/d from 8 May to 5 June.
  • Gullfaks will have 9.2mcm/d of unavailable capacity from 9 May to 4 June.
  • The Karsto processing facility will reduce capacity by 12.6mcm/d from 19 May to 1 June, 6.6mcm/d from 20-23 My and 17.6mcm/d on 20-23 May and with further outages scheduled in late May.
  • Troll will have a reduced capacity of 133mcm/d from 21-22 May, 46mcm/d on 22-23 May and 24 mcm/d from 23-24 May, and 19 mcm/d from 24-31 May.
  • The Kollsnes processing facility will reduce capacity by 158mcm/d on 21-22 May, 66mcm/d on 22-23 May and 42mcm/d on 23 May to 4 June.
  • Kvitebjørn will have a reduced capacity of 8.5mcm/d on 21-24 May.